I’m not sure that the stock market, yet, fully appreciates the pressure that the election put on AI stocks. And it couldn’t come at a much worse time, when Wall Street is questioning when AI companies, especially data center companies, will start producing the profits to justify their enormous capital spending.
The pressure comes from two directions.
From Congress and from the states. I’m much more worried about the impact of the elections at the state level right now because I think it will have a more immediate impact on the timing of revenue growth at hyperscalers and data centerr companies.
Newly elected governors in Ohio, Georgia, Michigan, New Mexico and Texas campaigned on a promise to stop–or at least pause-— data center construction statewide, while those in New York and Oregon pledged to prolong pauses already in place. All told, about 40% of pending data center capacity in the U.S. is planned to be built in states where newly elected governors have promised to stop or pause such construction, according to data from Cleanview, a market intelligence company.
That’s on top of 46 local ballot measures approved or on track to pass that also stall development, according to Bloomberg Economics; at least 17 of those are outright bans on large-scale data centers. Local opposition efforts had already hampered at least 45 projects in the second quarter of 2026, according to Data Center Watch, a research group.
“It was obviously not a very good night if you’re a data center developer,” said Bloomberg’s Justin Teresi.
Democrats now control key branches of state government in some of the country’s data center hotbeds, including Virginia, Pennsylvania and Arizona, and are likely to pursue utility and permitting policies that stall construction, according to a new report from Bloomberg.
Hyperscalers, the largest cloud-computing providers, are expected to overhaul and shift development plans in response. Tuesday’s results stand to shrink the $1.4 trillion that technology companies were expected to spend on AI infrastructure by roughly 5% to 7% in 2027, according to Bloomberg technology analyst Mandeep Singh. That includes spending on chips, networking equipment, land and other materials for data center construction. Those cuts and the anticipated slowdown in approvals may translate into as many as 10 gigawatts of data center capacity failing to come online next year as planned, Singh said.
Some planned projects will certainly switch states. Gordon Johnson of GLJ Research said in a note late Tuesday that Texas data center projects that don’t already have electricity and environmental permits lined up will “probably go to Louisiana, Oklahoma or nowhere.” That switching, though, will delay projects.
This pressure at the state level is in addition to efforts in Congress to speed up perrmitting but also to make data centers pay more of the energy cost. Data centers don’t get built in Washington. The permits, grid connection, tax break, and the rate it pays for electricity are all decided at the state level. Governors appoint the utility commissions in Texas and Ohio. In Georgia, the commissioners are elected, and Democrats just won the majority.
But Congress can tell grid operators in most parts of the country–the grid in Texas is a big exception–how to allocate electricty costs. As of November 16 Congress is considering at least three bills that would make data centers shoulder more of their electricity-infrastructure costs rather than spreading those costs across other customers. The most likely to pass is part of the Bipartisan American Affordability and Jobs Act, a broad energy-permitting package.
The package combines faster federal permitting of energy infrastructure projects with tougher payment requirements for large data centers. The faster permitting piece would change the National Environmental Policy Act, Clean Water Act and Endangered Species Act, as well as putting limits on lawsuits and on withdrawing permits after approval. Critics of the bill point that the bill’s streamlined permitting of gas pipelines would quickly facilitate gas-fired data-center projects, while the transmission improvements needed to deliver more clean electricity would take years.
The pricing part of the package would require the Federal Energy Regulatory Commission to issue rules within 90 days charging data centers both for grid upgrades needed to serve them and for their use of the existing transmission network, and give state regulators additional latitude to charge data centers more for building the power infrastructure they require and use the proceeds to reduce other customers’ bills.
How much would this cost AI companies? A Grid Strategies analysis estimated that the federal transmission provisions could shift an additional $35 billion of costs to data centers over ten years.
In total, the elections added delay at the state level and the prospect of higher energy costs at the federal level. Projects will take longer to build and the electricity they consume will cost more.

Doesn’t make sense to me that when any mega Corp or data center builds out a facility that the cost to provide substations, more power availability, etc. should in anyway be shouldered by the existing rate payers. Most likely these guys will get a discounted industrial rate anyway. The profit margins will be thinner for the provider than residential. – It’s not too much to ask for them to pay expenses of getting the utilities to them. Pay your share should apply to real estate developments and industries of all varieties.
They will generally get nice tax subsidies anyway which is usually an acceptable tradeoff for the expected gains from job growth. But, just what does their presence do for the ratepayers to make it reasonable for them to subsidize their expenses?